Part of The AI Infrastructure Reality Check.
On November 20, Corsair wanted $643.99 for a 32 GB kit it couldn’t ship. Two months earlier, a snapshot showed the same kit in stock at $559.99. The $84 difference is easy to calculate. What a buyer actually paid is still an open question.
The trail gets clearer at the factory. Micron says it moved some DRAM supply to data-center and cloud customers in response to AI demand, with an emphasis on high-bandwidth memory. In November 2026, TrendForce reported slow PC sales and rising inventories of finished PCs. It still expected PC DRAM contract prices to rise 13–18% quarter over quarter in Q4. PC makers can sell fewer computers and pay more for memory if suppliers cut allocations faster than orders fall. Micron FY2025 Form 10-K · TrendForce November PC procurement report
...
Six AI businesses and five tests of the boom
Part of The AI Infrastructure Reality Check.
NVIDIA reported $107.6 billion in Data Center revenue for the quarter ended October 25, 2026. For the quarter ended September 30, CoreWeave reported $3.66 billion in revenue and a $709 million net loss. Those totals cover different periods and different businesses. The chip supplier gets paid for hardware. The cloud operator needs to rent out capacity long enough to cover what it cost to put into service. NVIDIA Q3 FY2027 results · CoreWeave Q3 2026 results
...
GPU economics from break-even to cost per token
Part of The AI Infrastructure Reality Check.
In the model below, a GPU earns $2 an hour for 90% of the year and still finishes $1,212 short. The operator bought a share of the server and network along with the GPU and needs to recover that investment over four years. At $2.50 an hour, the same installation breaks even at about 77% billable time. The GPU break-even calculator lets you price your own assumptions.
...
What limits an AI cluster from delivery to peak load
Part of The AI Infrastructure Reality Check.
In the model below, the GPUs arrive in month 12. The operator can send its first bill in month 25. Move the delivery up four months and the invoice date stays put. Finish the grid work four months early and billing moves up one month. The delivery date on a purchase order tells you when the equipment gets to the site. Billing depends on when the operator has a working cluster the customer can accept.
...
AI infrastructure cash flow and who finances the buildout
Part of The AI Infrastructure Reality Check.
From the September 2025 quarter to the same quarter in 2026, Microsoft, Alphabet and Meta brought in $9.6 billion more operating cash. They spent $62.5 billion more on property and equipment. After those purchases, the three companies had $8.41 billion left between them, down from $61.29 billion a year earlier. Microsoft Form 10-Q · Alphabet results · Meta results
The bridge compares the same September quarter in each year. It uses consolidated cash flows and excludes the separate finance-lease adjustment.
...